HPH-Straub-Medical-Center-The-Project HPH-Straub-Medical-Center-The-Project

Straub Benioff Medical Center Construction Livestream

Video showing live progress of the Straub construction efforts in real time.

Livestream video of the Straub Benioff Medical Center in Honolulu.



Phase 1 - October 2023: Foundation pile testing for new parking building

Work on the foundation for the new parking building began in October 2023, including a deep foundation pile test using sectional augers.

...


Phase 1 - May 2023: Demolition of 800 S. King St.

Demolition work continued in May 2023 for the Straub Benioff Medical Center at 800 S. King St., the former location of the Straub Benioff Medical Center's Physical Therapy and Occupational Health services.

...


Phase 1 - April 2023: Demolition of 788 S. King St.

Construction crews made progress on the Straub Benioff Medical Center with the demolition of the building at 788 S. King St., the former BedMart location in April 2023.

...


Phase 1 - January and February 2023: Demolition of 801 S. Hotel St. and 793 S. Hotel St.

The Straub Benioff Medical Center begins with the demolition of the two-story building at 801 S. Hotel St. on January 26, 2023, followed by the neighboring building at 793 S. Hotel St.

...


Phase 1 - December 2022: Groundbreaking ceremony for Straub Benioff Medical Center

Straub Benioff Medical Center commemorated its 100th anniversary with an intimate groundbreaking to kick off a comprehensive redevelopment project of its campus. Kahu Kordell Kekoa led Hawaii Pacific Health leadership, HPH and Straub Benioff Medical Center board chairs, Straub Benioff Medical Center members and construction partners in a maile lei ceremony, land blessing, and groundbreaking ceremony.

...